Solid
Waste Management Sector - Investment Plan 2006-2012
Sl No |
DESCRIPTION |
EXPLANATION |
FUND |
2005-06 |
2006-07 |
2007-08 |
2008-09 |
2009-10 |
2010-11 |
2011-12 |
TOTAL |
1 |
AWARENESS cum LIVE MODEL DEMONSTRATION |
|
|
|
|
|
|
|
|
|
|
1 |
schools. |
sponsorship |
30% fund from sponsors |
0 |
6 |
10 |
5 |
2 |
2 |
2 |
27 |
1 |
Institution |
private participation |
fund given, to be repaid |
|
2.5 |
5 |
2.5 |
1 |
1 |
1 |
13 |
1 |
Community |
community participation |
fund given,to be repaid |
|
1 |
2.5 |
1.65 |
0.5 |
0.5 |
0.5 |
6.65 |
1 |
Biogas based Power |
ULB |
30%fund through sponsors |
|
1 |
1 |
|
|
|
|
2 |
2 |
Sludge Extraction and transport equipment for 1.2
to 1.4 |
private participation |
fund given, to be repaid |
|
0.3 |
0.3 |
0.3 |
|
|
|
0.9 |
2 |
SEGREGATION OF SOLID WASTE AT SOURCE: |
|
|
|
|
|
|
|
|
|
|
2 |
Domestic Waste Bins |
sponsorship |
30% fund from sponsors |
0 |
7.85 |
3.9 |
3.9 |
1.56 |
1.56 |
1.56 |
20.33 |
2 |
Domestic Vermi-composting units |
user to pay |
fund given,to be repaid |
0 |
0.16 |
0.08 |
0.08 |
0.08 |
0.08 |
0.08 |
0.56 |
2 |
Door to door primary collection |
user to pay |
pay.urban
poor employment |
|
|
|
|
|
|
|
|
3 |
SPECIAL PURPOSE VEHICLES |
|
|
|
|
|
|
|
|
|
|
3 |
SPVs |
private participation |
fund given,to be repaid |
|
3.9 |
1.95 |
1.95 |
0.78 |
0.78 |
0.78 |
10.14 |
3 |
Cleaning Service for SPVs |
private participation |
fund given,to be repaid |
|
0.39 |
0.18 |
0.21 |
0.09 |
0.09 |
0.09 |
1.05 |
4 |
SECONDARY COLLECTION: |
|
|
|
|
|
|
|
|
|
|
4 |
Secondary Collection |
private participation |
fund given,to be repaid |
|
1.9 |
1 |
0.9 |
0.4 |
0.4 |
0.4 |
5 |
4 |
Waste from institutions |
user to pay |
pay,urban
poor employement |
|
|
|
|
|
|
|
|
5 |
SLAUGHTER HOUSE/MAIN MARKET WASTE |
user to pay |
ULB /Private Fund |
|
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.7 |
6 |
LITTER BINS |
sponsors |
30%fund through sponsors |
0 |
0.39 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.54 |
7 |
INCINERATION UNITS |
users to pay |
fund given,to be repaid |
|
0.5 |
0.05 |
0.05 |
0.05 |
0.05 |
0.05 |
0.75 |
|
MAIN SOLID
WASTE PROCESSING AT BRAHMAPURAM |
|
|
|
|
|
|
|
|
|
|
8 |
WEIGHING MECHANISM |
ULB |
ULB fund |
|
2 |
|
|
|
|
|
2 |
9 |
SORTING BIO-NON-DEGRADABLE WASTE |
Private participation |
fund given,to be repaid |
|
2 |
|
|
|
|
|
2 |
10 |
COMPOSTING |
Private participation |
fund given,to be repaid |
|
1 |
1 |
1 |
1 |
1 |
1 |
6 |
11 |
BIO-METHANATION PLANT |
Private participation |
fund given,to be repaid |
|
3 |
3 |
3 |
|
|
|
9 |
12 |
ELECTRIC POWER GENERATION |
Private participation |
fund given,to be repaid |
|
4 |
4 |
4 |
2 |
2 |
2 |
18 |
13 |
SECURE LAND FILLING FACILITY |
Private participation |
fund given,to be repaid |
|
3 |
3 |
3 |
3 |
3 |
3 |
18 |
13 |
EXCAVATORS |
Private participation |
fund given,to be repaid |
|
0.32 |
|
|
|
|
|
0.32 |
14 |
EFFLUENT TREATMENT PLANT |
Private participation |
fund given,to be repaid |
|
|
6 |
|
|
|
|
6 |
15 |
DRINKING WATER AT MAIN PROCESSING SITE |
ULB |
fund given,to be repaid |
|
|
2 |
|
|
|
|
2 |
16 |
GREEN BELT &PICNIC SPOT |
Corporate participation |
fund given,to be repaid |
|
1 |
2 |
1 |
1 |
0.25 |
0.25 |
5.5 |
17 |
ENHANCING ROLE OF ULB STAFF |
ULB |
ULB |
|
|
2 |
3 |
3 |
1 |
1 |
10 |
17 |
IMPLEMENTATION OF COMPUTER SYSTEM |
ULB |
ULB |
|
2 |
|
|
|
|
|
2 |
18 |
BUILDING WASTE |
Private participation |
fund given,to be repaid |
|
|
0.48 |
0.12 |
0.12 |
0.12 |
0.12 |
0.96 |
TOTAL Rs. In Crores |
0 |
44.41 |
49.57 |
31.79 |
16.71 |
13.96 |
13.96 |
170.4 |